Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed
The objective of this study is to improve productivity of the assembly line in air conditioning compressor factory through Next Cell approach. One air conditioning compressor assembly factory had been chosen as a subject for the study. The subjects were non-productive (non-value added) jobs at the a...
Saved in:
Main Author: | |
---|---|
Format: | Thesis |
Language: | English |
Published: |
2010
|
Subjects: | |
Online Access: | https://ir.uitm.edu.my/id/eprint/65634/1/65634.pdf |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my-uitm-ir.65634 |
---|---|
record_format |
uketd_dc |
spelling |
my-uitm-ir.656342022-09-20T01:53:33Z Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed 2010 Mohamed, Mat Hisham Industrial productivity Dynamoelectric machinery and auxiliaries.Including generators, motors, transformers The objective of this study is to improve productivity of the assembly line in air conditioning compressor factory through Next Cell approach. One air conditioning compressor assembly factory had been chosen as a subject for the study. The subjects were non-productive (non-value added) jobs at the assembly section of the factory. The element examined was the productivity level which affected by non-productive or waste of the raw material, work-in-process, process cycle time and human motion. Four sets of data were collected during the study. The raw material and work-in-process data for the entire line were collected while the process cycle time and operator motion was analyzed and simulated by using line balancing and "Standard Operation Combination Table" (SOCT). The total line efficiency and productivity index was calculated. The process cycle time and operator motion analysis were conducted in order to obtain the relationship between the productivity and non-productive job. As a result, there is the productivity improvement with the elimination or reduction of established nonproductive job or waste. 2010 Thesis https://ir.uitm.edu.my/id/eprint/65634/ https://ir.uitm.edu.my/id/eprint/65634/1/65634.pdf text en public masters Universiti Teknologi MARA (UiTM) Faculty of Mechanical Engineering Omar, Abdul Rahman |
institution |
Universiti Teknologi MARA |
collection |
UiTM Institutional Repository |
language |
English |
advisor |
Omar, Abdul Rahman |
topic |
Industrial productivity Industrial productivity |
spellingShingle |
Industrial productivity Industrial productivity Mohamed, Mat Hisham Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed |
description |
The objective of this study is to improve productivity of the assembly line in air conditioning compressor factory through Next Cell approach. One air conditioning compressor assembly factory had been chosen as a subject for the study. The subjects were non-productive (non-value added) jobs at the assembly section of the factory. The element examined was the productivity level which affected by non-productive or waste of the raw material, work-in-process, process cycle time and human motion. Four sets of data were collected during the study. The raw material and work-in-process data for the entire line were collected while the process cycle time and operator motion was analyzed and simulated by using line balancing and "Standard Operation Combination Table" (SOCT). The total line efficiency and productivity index was calculated. The process cycle time and operator motion analysis were conducted in order to obtain the relationship between the productivity and non-productive job. As a result, there is the productivity improvement with the elimination or reduction of established nonproductive job or waste. |
format |
Thesis |
qualification_level |
Master's degree |
author |
Mohamed, Mat Hisham |
author_facet |
Mohamed, Mat Hisham |
author_sort |
Mohamed, Mat Hisham |
title |
Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed |
title_short |
Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed |
title_full |
Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed |
title_fullStr |
Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed |
title_full_unstemmed |
Productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / Mat Hisham Mohamed |
title_sort |
productivity improvement through "next cell" approach: a study case at motor winding assembly line of air conditioning compressor / mat hisham mohamed |
granting_institution |
Universiti Teknologi MARA (UiTM) |
granting_department |
Faculty of Mechanical Engineering |
publishDate |
2010 |