Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry

The construction industry has rapidly grown in Saudi Arabia and there are many upcoming projects to be finished in a limited time to meet the Saudi Vision 2030. Due to the shortage of time, most of the projects are managed by fast track system. It has been observed that the number and amount of c...

Full description

Saved in:
Bibliographic Details
Main Author: Shaikh, Haseeb Halim
Format: Thesis
Language:English
English
English
Published: 2021
Subjects:
Online Access:http://eprints.uthm.edu.my/6439/1/24p%20HASEEB%20HALEEM%20SHAIKH.pdf
http://eprints.uthm.edu.my/6439/2/HASEEB%20HALEEM%20SHAIKH%20COPYRIGHT%20DECLARATION.pdf
http://eprints.uthm.edu.my/6439/3/HASEEB%20HALEEM%20SHAIKH%20WATERMARK.pdf
Tags: Add Tag
No Tags, Be the first to tag this record!
id my-uthm-ep.6439
record_format uketd_dc
spelling my-uthm-ep.64392022-02-05T07:29:13Z Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry 2021-05 Shaikh, Haseeb Halim T Technology (General) TH5011-5701 Construction by phase of the work (Building trades) The construction industry has rapidly grown in Saudi Arabia and there are many upcoming projects to be finished in a limited time to meet the Saudi Vision 2030. Due to the shortage of time, most of the projects are managed by fast track system. It has been observed that the number and amount of construction claims are increasing in Saudi Arabian construction industry. The existing studies lacks in claims management especially on fast track projects in Saudi Arabia due to governance system. Therefore, this research aims to control the possible claims and provide suggestions to improve the project performance by better claim management approach in Saudi Arabian construction industry. Hence, this study investigates and evaluates the major types and causes of claims that occur especially in the fast track mega infrastructure projects of Saudi Arabia. It also provides remedial measures to deal with claims of such projects. Detailed literature has been carried out to identify the types and causes of claims affecting the fast track projects followed by questionnaires survey. The data was collected from the Riyadh Metro project and was analyzed by Average Mean Index (AMI) method using SPSS and Analytical Hierarchy Process (AHP) using Expert Choice. The remedial measures were suggested based on targeted experts’ opinion. This research concluded that major causes of claims on fast track mega projects were unclear scope of work, incomplete contract documents, design change by the client and unforeseen underground utilities. This study suggested that the claim management process should be implemented in construction projects while dealing with claims, especially in the fast track mega infrastructure projects of the Saudi Arabian construction industry. Early identification of claims helps the stakeholders to resolve the issues immediately. The findings of this research will be assisting the construction professionals and Saudi government to deal with the upcoming fast track mega projects such as Makkah Metro, Jeddah Metro and Dammam Metro projects. 2021-05 Thesis http://eprints.uthm.edu.my/6439/ http://eprints.uthm.edu.my/6439/1/24p%20HASEEB%20HALEEM%20SHAIKH.pdf text en public http://eprints.uthm.edu.my/6439/2/HASEEB%20HALEEM%20SHAIKH%20COPYRIGHT%20DECLARATION.pdf text en staffonly http://eprints.uthm.edu.my/6439/3/HASEEB%20HALEEM%20SHAIKH%20WATERMARK.pdf text en validuser mphil masters Universiti Tun Hussein Malaysia Fakulti Sains Gunaan dan Teknologi
institution Universiti Tun Hussein Onn Malaysia
collection UTHM Institutional Repository
language English
English
English
topic T Technology (General)
TH5011-5701 Construction by phase of the work (Building trades)
spellingShingle T Technology (General)
TH5011-5701 Construction by phase of the work (Building trades)
Shaikh, Haseeb Halim
Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry
description The construction industry has rapidly grown in Saudi Arabia and there are many upcoming projects to be finished in a limited time to meet the Saudi Vision 2030. Due to the shortage of time, most of the projects are managed by fast track system. It has been observed that the number and amount of construction claims are increasing in Saudi Arabian construction industry. The existing studies lacks in claims management especially on fast track projects in Saudi Arabia due to governance system. Therefore, this research aims to control the possible claims and provide suggestions to improve the project performance by better claim management approach in Saudi Arabian construction industry. Hence, this study investigates and evaluates the major types and causes of claims that occur especially in the fast track mega infrastructure projects of Saudi Arabia. It also provides remedial measures to deal with claims of such projects. Detailed literature has been carried out to identify the types and causes of claims affecting the fast track projects followed by questionnaires survey. The data was collected from the Riyadh Metro project and was analyzed by Average Mean Index (AMI) method using SPSS and Analytical Hierarchy Process (AHP) using Expert Choice. The remedial measures were suggested based on targeted experts’ opinion. This research concluded that major causes of claims on fast track mega projects were unclear scope of work, incomplete contract documents, design change by the client and unforeseen underground utilities. This study suggested that the claim management process should be implemented in construction projects while dealing with claims, especially in the fast track mega infrastructure projects of the Saudi Arabian construction industry. Early identification of claims helps the stakeholders to resolve the issues immediately. The findings of this research will be assisting the construction professionals and Saudi government to deal with the upcoming fast track mega projects such as Makkah Metro, Jeddah Metro and Dammam Metro projects.
format Thesis
qualification_name Master of Philosophy (M.Phil.)
qualification_level Master's degree
author Shaikh, Haseeb Halim
author_facet Shaikh, Haseeb Halim
author_sort Shaikh, Haseeb Halim
title Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry
title_short Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry
title_full Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry
title_fullStr Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry
title_full_unstemmed Construction claims in the fast track mega infrastructure projects of Saudi Arabian Construction Industry
title_sort construction claims in the fast track mega infrastructure projects of saudi arabian construction industry
granting_institution Universiti Tun Hussein Malaysia
granting_department Fakulti Sains Gunaan dan Teknologi
publishDate 2021
url http://eprints.uthm.edu.my/6439/1/24p%20HASEEB%20HALEEM%20SHAIKH.pdf
http://eprints.uthm.edu.my/6439/2/HASEEB%20HALEEM%20SHAIKH%20COPYRIGHT%20DECLARATION.pdf
http://eprints.uthm.edu.my/6439/3/HASEEB%20HALEEM%20SHAIKH%20WATERMARK.pdf
_version_ 1747831063242080256