Notice condition precedent to claim liquidated ascertained damages (LAD)

Most forms of building contract include a clause entitling the employer to a specified amount of damages, referred to as liquidated and ascertained damages (LAD) if the contractor is late in constructing a project. This clause sets out the procedure and condition that need to be followed by the empl...

Full description

Saved in:
Bibliographic Details
Main Author: Mansor, Nur Syaimasyaza
Format: Thesis
Language:English
Published: 2011
Subjects:
Online Access:http://eprints.utm.my/id/eprint/36798/1/NurSyaimasyazaMansorMFAB2011.pdf
Tags: Add Tag
No Tags, Be the first to tag this record!
id my-utm-ep.36798
record_format uketd_dc
spelling my-utm-ep.367982018-05-27T08:14:28Z Notice condition precedent to claim liquidated ascertained damages (LAD) 2011 Mansor, Nur Syaimasyaza TH Building construction Most forms of building contract include a clause entitling the employer to a specified amount of damages, referred to as liquidated and ascertained damages (LAD) if the contractor is late in constructing a project. This clause sets out the procedure and condition that need to be followed by the employer. Some provision for example in clause 40.1 PWD 203A (Rev. 2007) require the employer to issue notice of intention before claiming LAD. The purpose of the issuance of notice is to inform the contractor about the payment or deduction. However, does the issuance of notice is condition precedent to the said claim? Some provision does not specifically expressly state the requirement to issue notice. So, there is an argument that section 56(3) of Contract Act is effective as an implied term to the contract. Based on the respective situations, question arises whether the employer?s entitlement to liquidated damages is waived if he fails to issue the said notice. This study is carried out to determine whether notice is condition precedent to claim liquidated damages and the legal impact of notice provision for liquidated damages claim. The study was carried out mainly through documentary analysis of law journals. It was found that when the provision expressly state that notice is condition precedent, the failure to comply with notice provision might jeopardize the employer?s claim. However, the employer?s claim is not totally rejected because based on prevention principle, the contractor who caused the delay, cannot benefit from its wrong act. When the provision did not expressly state that notice is a condition precedent, it can be condition precedent by implication. The argument that section 56(3) is an implied term to the contract was wrong because section 56(3) is only applicable when the contract becomes voidable. 2011 Thesis http://eprints.utm.my/id/eprint/36798/ http://eprints.utm.my/id/eprint/36798/1/NurSyaimasyazaMansorMFAB2011.pdf application/pdf en public http://dms.library.utm.my:8080/vital/access/manager/Repository/vital:74152?queryType=vitalDismax&query=Notice+condition+precedent+to+claim+liquidated+ascertained+damages+%28LAD%29&public=true masters Universiti Teknologi Malaysia, Faculty of Built Environment Faculty of Built Environment
institution Universiti Teknologi Malaysia
collection UTM Institutional Repository
language English
topic TH Building construction
spellingShingle TH Building construction
Mansor, Nur Syaimasyaza
Notice condition precedent to claim liquidated ascertained damages (LAD)
description Most forms of building contract include a clause entitling the employer to a specified amount of damages, referred to as liquidated and ascertained damages (LAD) if the contractor is late in constructing a project. This clause sets out the procedure and condition that need to be followed by the employer. Some provision for example in clause 40.1 PWD 203A (Rev. 2007) require the employer to issue notice of intention before claiming LAD. The purpose of the issuance of notice is to inform the contractor about the payment or deduction. However, does the issuance of notice is condition precedent to the said claim? Some provision does not specifically expressly state the requirement to issue notice. So, there is an argument that section 56(3) of Contract Act is effective as an implied term to the contract. Based on the respective situations, question arises whether the employer?s entitlement to liquidated damages is waived if he fails to issue the said notice. This study is carried out to determine whether notice is condition precedent to claim liquidated damages and the legal impact of notice provision for liquidated damages claim. The study was carried out mainly through documentary analysis of law journals. It was found that when the provision expressly state that notice is condition precedent, the failure to comply with notice provision might jeopardize the employer?s claim. However, the employer?s claim is not totally rejected because based on prevention principle, the contractor who caused the delay, cannot benefit from its wrong act. When the provision did not expressly state that notice is a condition precedent, it can be condition precedent by implication. The argument that section 56(3) is an implied term to the contract was wrong because section 56(3) is only applicable when the contract becomes voidable.
format Thesis
qualification_level Master's degree
author Mansor, Nur Syaimasyaza
author_facet Mansor, Nur Syaimasyaza
author_sort Mansor, Nur Syaimasyaza
title Notice condition precedent to claim liquidated ascertained damages (LAD)
title_short Notice condition precedent to claim liquidated ascertained damages (LAD)
title_full Notice condition precedent to claim liquidated ascertained damages (LAD)
title_fullStr Notice condition precedent to claim liquidated ascertained damages (LAD)
title_full_unstemmed Notice condition precedent to claim liquidated ascertained damages (LAD)
title_sort notice condition precedent to claim liquidated ascertained damages (lad)
granting_institution Universiti Teknologi Malaysia, Faculty of Built Environment
granting_department Faculty of Built Environment
publishDate 2011
url http://eprints.utm.my/id/eprint/36798/1/NurSyaimasyazaMansorMFAB2011.pdf
_version_ 1747816460223250432