Comparison for components of cost overrun in construction

Construction industry is considered as one of the most important industries in China. It is well known that most construction projects in China are exposed to cost overrun. From the literature review, forty-three general cost overrun factors in construction projects were obtained based on previous r...

Full description

Saved in:
Bibliographic Details
Main Author: Liu, Linbo
Format: Thesis
Language:English
Published: 2014
Subjects:
Online Access:http://eprints.utm.my/id/eprint/48377/25/LiuLinboMFKA2014.pdf
Tags: Add Tag
No Tags, Be the first to tag this record!
id my-utm-ep.48377
record_format uketd_dc
spelling my-utm-ep.483772017-09-12T04:24:39Z Comparison for components of cost overrun in construction 2014 Liu, Linbo HD Industries. Land use. Labor Construction industry is considered as one of the most important industries in China. It is well known that most construction projects in China are exposed to cost overrun. From the literature review, forty-three general cost overrun factors in construction projects were obtained based on previous researches from many countries. The aim of this study is to evaluate the most important cost overrun factors that are specifically related to resources, namely labour, material, equipment and subcontractor. Two questionnaire surveys were used to achieve the objectives in this study. The first questionnaire was designed to determine the severity of cost overrun factors, and the second one was designed to obtain the proportions of cost components and top-ten factors cost for each component. Data from the questionnaires were analysed by using the relative importance index (RII) method and mean value method. The findings indicated that material cost is the highest, and subcontractor cost is the lowest, while equipment and labour cost are approximately the same. Low productivity of labour, lack of skilled labour, escalation of material prices, material quality issues, high cost of machineries and poor cash flow management are among the important factors for cost overrun. This study concludes factors that cause cost overrun in China are similar to those that can be found in other countries except for a few factors. These factors are rework due to error in construction, equipment breakdown, improper planning, project management and contract administration, high level of quality requirement, and project schedule changes. This study can be used as reference for the further studies to evaluate the causes of cost overrun in construction projects and minimise the associated risk 2014 Thesis http://eprints.utm.my/id/eprint/48377/ http://eprints.utm.my/id/eprint/48377/25/LiuLinboMFKA2014.pdf application/pdf en public masters Universiti Teknologi Malaysia, Faculty of Civil Engineering Faculty of Civil Engineering
institution Universiti Teknologi Malaysia
collection UTM Institutional Repository
language English
topic HD Industries
Land use
Labor
spellingShingle HD Industries
Land use
Labor
Liu, Linbo
Comparison for components of cost overrun in construction
description Construction industry is considered as one of the most important industries in China. It is well known that most construction projects in China are exposed to cost overrun. From the literature review, forty-three general cost overrun factors in construction projects were obtained based on previous researches from many countries. The aim of this study is to evaluate the most important cost overrun factors that are specifically related to resources, namely labour, material, equipment and subcontractor. Two questionnaire surveys were used to achieve the objectives in this study. The first questionnaire was designed to determine the severity of cost overrun factors, and the second one was designed to obtain the proportions of cost components and top-ten factors cost for each component. Data from the questionnaires were analysed by using the relative importance index (RII) method and mean value method. The findings indicated that material cost is the highest, and subcontractor cost is the lowest, while equipment and labour cost are approximately the same. Low productivity of labour, lack of skilled labour, escalation of material prices, material quality issues, high cost of machineries and poor cash flow management are among the important factors for cost overrun. This study concludes factors that cause cost overrun in China are similar to those that can be found in other countries except for a few factors. These factors are rework due to error in construction, equipment breakdown, improper planning, project management and contract administration, high level of quality requirement, and project schedule changes. This study can be used as reference for the further studies to evaluate the causes of cost overrun in construction projects and minimise the associated risk
format Thesis
qualification_level Master's degree
author Liu, Linbo
author_facet Liu, Linbo
author_sort Liu, Linbo
title Comparison for components of cost overrun in construction
title_short Comparison for components of cost overrun in construction
title_full Comparison for components of cost overrun in construction
title_fullStr Comparison for components of cost overrun in construction
title_full_unstemmed Comparison for components of cost overrun in construction
title_sort comparison for components of cost overrun in construction
granting_institution Universiti Teknologi Malaysia, Faculty of Civil Engineering
granting_department Faculty of Civil Engineering
publishDate 2014
url http://eprints.utm.my/id/eprint/48377/25/LiuLinboMFKA2014.pdf
_version_ 1747817375407800320