The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia

Sanitation infrastructure in Indonesia is conventionally procured using the traditional method. Due to sequential nature of this method, it can result in a lengthy design and construction period. Design and Build (DB) procurement method can be considered as one of the solutions since this method has...

Full description

Saved in:
Bibliographic Details
Main Author: Perkasa, Muhammad Iqbal
Format: Thesis
Language:English
Published: 2015
Subjects:
Online Access:http://eprints.utm.my/id/eprint/79403/1/MuhammadIqbalPerkasaMFAB2015.pdf
Tags: Add Tag
No Tags, Be the first to tag this record!
id my-utm-ep.79403
record_format uketd_dc
spelling my-utm-ep.794032018-10-16T07:30:34Z The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia 2015 Perkasa, Muhammad Iqbal HT Communities. Classes. Races Sanitation infrastructure in Indonesia is conventionally procured using the traditional method. Due to sequential nature of this method, it can result in a lengthy design and construction period. Design and Build (DB) procurement method can be considered as one of the solutions since this method has been claimed as a method that offers: improved buildability, faster completion of time, and greater certainty in price. The Directorate of Environmental Sanitation Development, Ministry Of Public Work (MOPW) is the body that is responsible on sanitation infrastructure. Thus, the aim of this study is to determine the potential of Design and Build method procurement implementation in Directorate of Environmental Sanitation Development by identifying the potential barriers to implementing design and build procurement method and the critical success factors (CSFs) with strong predictive powers of its implementation particularly in sanitation infrastructure. The data collected for this study is generated from structured interviews that have been conducted among the experts who have sufficient knowledge and substantial experience of project delivery system in Indonesia. The study found that among others, the factors include “lack of experience”, “lack of regulation on contractual arrangement”, “lack of detailed regulation on tendering system”, “lack of detailed guideline on project characteristics” and “a small number of experienced and skilled of other stakeholders in DB” as potential barriers that can impede the implementation of DB system. The experts also identified “comprehensive contract form and documentation”, “well defined project scope definition, “client‟s input in the project”, “contractor‟s competence”, “experienced project team leader”, “and working relationship among project team members” as CSFs that need to be paid more attention on to in order to enhance the successfulness of the Design and Build project. Moreover, those factors are needed to be given more attention to enhance the potential of DB procurement method implementation in the Directorate of Environmental Sanitation Development, MOPW. 2015 Thesis http://eprints.utm.my/id/eprint/79403/ http://eprints.utm.my/id/eprint/79403/1/MuhammadIqbalPerkasaMFAB2015.pdf application/pdf en public masters Universiti Teknologi Malaysia, Faculty of Built Environment Faculty of Built Environment
institution Universiti Teknologi Malaysia
collection UTM Institutional Repository
language English
topic HT Communities
Classes
Races
spellingShingle HT Communities
Classes
Races
Perkasa, Muhammad Iqbal
The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia
description Sanitation infrastructure in Indonesia is conventionally procured using the traditional method. Due to sequential nature of this method, it can result in a lengthy design and construction period. Design and Build (DB) procurement method can be considered as one of the solutions since this method has been claimed as a method that offers: improved buildability, faster completion of time, and greater certainty in price. The Directorate of Environmental Sanitation Development, Ministry Of Public Work (MOPW) is the body that is responsible on sanitation infrastructure. Thus, the aim of this study is to determine the potential of Design and Build method procurement implementation in Directorate of Environmental Sanitation Development by identifying the potential barriers to implementing design and build procurement method and the critical success factors (CSFs) with strong predictive powers of its implementation particularly in sanitation infrastructure. The data collected for this study is generated from structured interviews that have been conducted among the experts who have sufficient knowledge and substantial experience of project delivery system in Indonesia. The study found that among others, the factors include “lack of experience”, “lack of regulation on contractual arrangement”, “lack of detailed regulation on tendering system”, “lack of detailed guideline on project characteristics” and “a small number of experienced and skilled of other stakeholders in DB” as potential barriers that can impede the implementation of DB system. The experts also identified “comprehensive contract form and documentation”, “well defined project scope definition, “client‟s input in the project”, “contractor‟s competence”, “experienced project team leader”, “and working relationship among project team members” as CSFs that need to be paid more attention on to in order to enhance the successfulness of the Design and Build project. Moreover, those factors are needed to be given more attention to enhance the potential of DB procurement method implementation in the Directorate of Environmental Sanitation Development, MOPW.
format Thesis
qualification_level Master's degree
author Perkasa, Muhammad Iqbal
author_facet Perkasa, Muhammad Iqbal
author_sort Perkasa, Muhammad Iqbal
title The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia
title_short The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia
title_full The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia
title_fullStr The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia
title_full_unstemmed The potential of design and build procurement method implemention in the directorate of enviromental sanitation development Indonesia
title_sort potential of design and build procurement method implemention in the directorate of enviromental sanitation development indonesia
granting_institution Universiti Teknologi Malaysia, Faculty of Built Environment
granting_department Faculty of Built Environment
publishDate 2015
url http://eprints.utm.my/id/eprint/79403/1/MuhammadIqbalPerkasaMFAB2015.pdf
_version_ 1747818219611095040