Backup distance protection coordination for three terminal HV transmission line considering main protection failure

The protection system scheme in transmission line is very important to maintain security and reliability of power system. This research will focus on the protection scheme at the three terminal transmission line such as 132kV and 275kV that implement in Malaysia utility and propose a new distance pr...

Full description

Saved in:
Bibliographic Details
Main Author: Mohd. Razali, Mohd. Razani
Format: Thesis
Language:English
Published: 2021
Subjects:
Online Access:http://eprints.utm.my/id/eprint/99491/1/MohdRazaniRazaliMKE2021.pdf
Tags: Add Tag
No Tags, Be the first to tag this record!
id my-utm-ep.99491
record_format uketd_dc
spelling my-utm-ep.994912023-02-27T07:44:39Z Backup distance protection coordination for three terminal HV transmission line considering main protection failure 2021 Mohd. Razali, Mohd. Razani TK Electrical engineering. Electronics Nuclear engineering The protection system scheme in transmission line is very important to maintain security and reliability of power system. This research will focus on the protection scheme at the three terminal transmission line such as 132kV and 275kV that implement in Malaysia utility and propose a new distance protection system scheme. The backup protection schemes in Malaysia utility has a higher fault clearing time. This research will focus on backup protection operation of three terminal overhead transmission line for all condition with considering main protection fail, DC supply fail or communication fail. Therefore, this study will propose and improve the backup protection scheme, two components will consider which are fault clearing time and distance relay zone configuration. Each improvement has own philosophy and concreate reason to determine advantages for backup protection scheme in three terminal transmission line. The effect for improvement need to ensure time coordination did not overlap with others scheme. To analyse existing and new protection scheme in this study, ETAP software will be use. All decision of fault clearing time and zone coverage can generate by ETAP simulation. The propose method able to help utility to have better fault clearing time and zone of coverage. 2021 Thesis http://eprints.utm.my/id/eprint/99491/ http://eprints.utm.my/id/eprint/99491/1/MohdRazaniRazaliMKE2021.pdf application/pdf en public http://dms.library.utm.my:8080/vital/access/manager/Repository/vital:149796 masters Universiti Teknologi Malaysia Faculty of Engineering - School of Electrical Engineering
institution Universiti Teknologi Malaysia
collection UTM Institutional Repository
language English
topic TK Electrical engineering
Electronics Nuclear engineering
spellingShingle TK Electrical engineering
Electronics Nuclear engineering
Mohd. Razali, Mohd. Razani
Backup distance protection coordination for three terminal HV transmission line considering main protection failure
description The protection system scheme in transmission line is very important to maintain security and reliability of power system. This research will focus on the protection scheme at the three terminal transmission line such as 132kV and 275kV that implement in Malaysia utility and propose a new distance protection system scheme. The backup protection schemes in Malaysia utility has a higher fault clearing time. This research will focus on backup protection operation of three terminal overhead transmission line for all condition with considering main protection fail, DC supply fail or communication fail. Therefore, this study will propose and improve the backup protection scheme, two components will consider which are fault clearing time and distance relay zone configuration. Each improvement has own philosophy and concreate reason to determine advantages for backup protection scheme in three terminal transmission line. The effect for improvement need to ensure time coordination did not overlap with others scheme. To analyse existing and new protection scheme in this study, ETAP software will be use. All decision of fault clearing time and zone coverage can generate by ETAP simulation. The propose method able to help utility to have better fault clearing time and zone of coverage.
format Thesis
qualification_level Master's degree
author Mohd. Razali, Mohd. Razani
author_facet Mohd. Razali, Mohd. Razani
author_sort Mohd. Razali, Mohd. Razani
title Backup distance protection coordination for three terminal HV transmission line considering main protection failure
title_short Backup distance protection coordination for three terminal HV transmission line considering main protection failure
title_full Backup distance protection coordination for three terminal HV transmission line considering main protection failure
title_fullStr Backup distance protection coordination for three terminal HV transmission line considering main protection failure
title_full_unstemmed Backup distance protection coordination for three terminal HV transmission line considering main protection failure
title_sort backup distance protection coordination for three terminal hv transmission line considering main protection failure
granting_institution Universiti Teknologi Malaysia
granting_department Faculty of Engineering - School of Electrical Engineering
publishDate 2021
url http://eprints.utm.my/id/eprint/99491/1/MohdRazaniRazaliMKE2021.pdf